#AT1245. A - Task Scheduling Problem

A - Task Scheduling Problem

A - Task Scheduling Problem

Score : $100$ points

Problem Statement

You have three tasks, all of which need to be completed.

First, you can complete any one task at cost $0$.

Then, just after completing the $i$-th task, you can complete the $j$-th task at cost $|A_j - A_i|$.

Here, $|x|$ denotes the absolute value of $x$.

Find the minimum total cost required to complete all the task.

Constraints

  • All values in input are integers.
  • $1 \leq A_1, A_2, A_3 \leq 100$

Input

Input is given from Standard Input in the following format:

A1A_1 A2A_2 A3A_3

Output

Print the minimum total cost required to complete all the task.


1 6 3
5

When the tasks are completed in the following order, the total cost will be $5$, which is the minimum:

  • Complete the first task at cost $0$.
  • Complete the third task at cost $2$.
  • Complete the second task at cost $3$.

11 5 5
6

100 100 100
0